Endangered species issues slow pipeline completion

The following article by Robert M. Stonestreet of Babst Calland appears in the March 2022 issue of The Practical Operator.

The federal Fourth Circuit Court of Appeals has struck down an evaluation by the U.S. Fish and Wildlife Service (FWS) of the potential impacts on two endangered fish species presented by stream crossings for the Mountain Valley Pipeline. In its February 3 opinion, the court concluded that the FWS failed to sufficiently establish the “environmental baseline” conditions for each species and failed to adequately evaluate how the stream crossings, along with other anticipated activities impacting the streams, will affect the species on a cumulative basis. The court also faulted the agency for not assuming future negative effects of climate change in its analysis.

In September 2020, the FWS published a “Biological Opinion” addressing how the proposed pipeline would likely affect five species (one plant, two fish and two bat) listed for protection under the federal Endangered Species Act (ESA). The FWS concluded that the pipeline would likely affect each species, but would not jeopardize those species, which is the key determination under the ESA for whether other federal agencies may issue permits for a project. The FWS also issued an “Incidental Take Statement” that authorized certain levels of “take” of each species associated with construction of the stream crossings, which would otherwise be prohibited by the ESA. For purposes of the ESA, “take” of a species means actions “to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect, or to attempt to engage in any such conduct.”

A group of organizations opposed to the pipeline, including the Sierra Club, challenged both the Biological Opinion and the Incidental Take Statement with regard to the two fish species (Roanoke Logperch and Candy Darter) and one bat species (Indiana Bat). The court only squarely addressed the FWS’s evaluation of the two fish species, but included a detailed footnote that strongly recommended a second look by the FWS at its evaluation of the Indiana Bat.

The opinion explaining the court’s ruling primarily focuses on how the FWS ascertained the environmental baseline for the two fish species and assessed the cumulative impacts of the proposed pipeline along with other anticipated activities. The court faulted the FWS for not gathering site-specific data for each stream crossing proposed in areas of the species’ habitat. The opinion states that the FWS did not sufficiently identify the existing “stressors” that were negatively impacting the species in the pipeline path. Although the FWS observed that a primary driver decreasing the Candy Darter population is “hybridization”―i.e. interbreeding by the Candy Darter with another similar species of darter―the court concluded that the FWS did not adequately consider other factors negatively affecting the Candy Darter, such as increased stream sedimentation.

The court rejected the agency’s argument that statistical modeling used to prepare both the environmental baseline determination and cumulative effects evaluation sufficiently accounted for conditions within the pipeline path. The court did so because (1) the Biological Opinion does not indicate a reliance on statistical modeling to establish the environmental baseline or cumulative effects determinations; and (2) the models were not designed to assess environmental conditions on a small-enough scale to evaluate the specific areas to be impacted by the project.

With respect to climate change, the court acknowledged that the statistical modeling used by the FWS takes into account “environmental stochasticity,” which is defined as “unpredictable fluctuations in environmental conditions.” The court still found that the agency did not adequately consider climate change because the models assumed a constant amount of environmental stochasticity in the future. According to the court, “the model failed to account for the one thing we know about climate change: that it will get worse over time.” The opinion identifies anticipated increased water temperatures, frequency and intensity of flooding, and increased sedimentation as negative impacts of climate change that were not considered in the statistical models. The court does not cite to any of the materials in the administrative record to support this observation. Other than referencing a description of climate change by the FWS as presenting an “increasing threat,” the court does not offer any guidance on why the agency should assume conditions for the species will necessarily get “worse” over time due to climate change, or how the FWS should go about factoring these considerations into its evaluations.

In light of the FWS’s shortcomings described in the opinion, the court concluded that the agency could not have reasonably concluded that the proposed project is unlikely to jeopardize the two fish species. The court recognized that the ESA does not prohibit approval of projects “solely because baseline conditions or cumulative effects already imperil a species.” However, the ESA does prohibit approval of a project that will likely accelerate the decline of a species. “Put differently, if a species is already speeding toward the extinction cliff, an agency may not press on the gas.”

The court rejected several additional arguments advanced by the challengers as grounds to set aside the Biological Opinion and Incidental Take Statement. These included claims that the FWS (1) arbitrarily limited the scope of the “action area” (i.e. the impact area); (2) erroneously excluded the Blackwater River from its evaluation of the Roanoke Logperch; and (3) the Incidental Take Statement established “unlawfully vague” take limits.

This opinion highlights the importance of Endangered Species Act considerations for energy projects. The Candy Darter was listed as endangered on November 20, 2018, which was more than a year after the Federal Energy Regulatory Commission (FERC) authorized the pipeline project. As noted in the 2021 Babst Calland Report, the FWS has drastically accelerated the pace of proposing and adopting species for protection under the ESA. As more species are designated for protection under the ESA, there is an increased likelihood that areas slated for development will trigger a rigorous review by the FWS before any federal permit may be issued for a proposed project.

The opinion makes clear that the Fish and Wildlife Service must methodically analyze the specific areas expected to be affected by a proposed project to determine whether the project may jeopardize a listed species. This effectively means that project proponents, through their counsel and consultants, must ensure that the FWS adequately evaluates potential impacts on listed species, and more importantly, documents that evaluation correctly. A failure by the FWS to do so, or a finding that the project will jeopardize a listed species, can stop a project in its tracks. Even one that is “an already mostly finished Pipeline” as the court observed in this case. As of December 2021, 94 percent of the pipeline had been constructed with approximately 20 linear miles remaining.

>> Return to the Latest News and Blog index page >>


Want to continue to get all the insider oil and gas news? Become a PIOGA member and you’ll get access to The PIOGA Press monthly newsletter, the PIOGA eWeekly e-newsletter and many other member benefits. Click here to learn more and join today!

2022-03-11T16:10:25-05:00
Go to Top